ROAD DEPARTMENT
SUBJECT: Bid Award for Center Road CR 215 Rehab C Hot Mix Asphalt Overlay Project.
FISCAL IMPACT: Funding is available within the current 2021/2022 Fiscal Year Road Construction Budget Unit No. 122-1222.
ACTION REQUESTED: 1) Award the contract for “Center Road CR 215 Rehab C Hot Mix Asphalt Overlay Project” to Hat Creek Construction & Materials, Inc., the only bidder meeting the specifications in the amount of $3,098,289; and 2) authorize the Director of Public Works to sign the agreement upon approval as to form by County Counsel; and 3) authorize the Director of Public Works to authorize Change Orders up to a “not-to-exceed” amount of $464,743 (approximately 15%) or a total contract not-to-exceed cost of $3,563,032.
|